Site + foundation
Survey, clearing, grading, drainage, excavation, utilities, foundation and conditions below grade.
Start with the latest Census contractor-built benchmark. Then separate the house, site, soft costs, local context and reserve—before a single total hides what is missing.
Start with the Census contractor-built benchmark, then expose locality, finish, complexity and the costs the contract may leave out.
Typical planning total $401,420 · $201/sq ft including entered additions and reserve.
Benchmark: 2025 Census average contract price of $198.33/sq ft for contractor-built single-family houses started. Census says the contract price excludes the improved lot. This planning model is not a builder bid, appraisal, loan decision or promise of final cost.
Use the benchmark as a starting point, then verify every phase against drawings and equal-scope bids.
Survey, clearing, grading, drainage, excavation, utilities, foundation and conditions below grade.
Framing, roof, exterior walls, windows and exterior doors that create a weather-tight shell.
Mechanical, electrical, plumbing, insulation, air sealing, drywall and required inspections.
Cabinetry, surfaces, fixtures, flooring, paint, testing, corrections and occupancy documentation.
The core calculation multiplies conditioned square feet by the Census 2025 average contract price per square foot, the selected state installation factor, finish factor and complexity factor. It then adds only the separate amounts you enter and a visible contingency.
The low and high results place a ±15% band around modeled hard construction. That band is a HomeCostGrid planning assumption, not a Census confidence interval or prediction.
The 2025 U.S. Census table reports a $171.57 median and $198.33 average contract price per square foot for new contractor-built single-family houses started. Census excludes the value of the improved lot. Your design, site and contract can differ materially.
No. Land is excluded. Enter site work, design, permits and utility connections only when they are outside the base construction contract, and avoid double-counting an included line.
Before drawings, soil information, bids and local fees exist, one exact number creates false confidence. The range keeps ordinary scope uncertainty visible while preserving your entered costs.
No. It is a planning model for comparing scope and preparing questions. Only address-specific plans, investigations, written bids and official fee information can support a project budget.